Knock Down Rebuild: The Full Sequence and the Demolition Stage

A Sydney knock down rebuild takes 12 to 18 months. The full sequence stage by stage, what happens in the demolition stage and why approval comes first.

Excavator demolishing a weatherboard house ahead of a knock down rebuild

A knock down rebuild in Sydney usually takes 12 to 18 months end to end. Design and approval account for roughly 4 to 8 months, demolition and clearance 5 to 15 working days, and construction 8 to 12 months. The demolition is the shortest phase and the one that gates everything after it.

One rule governs the whole sequence: you cannot demolish before the approval for the new dwelling exists. George Saratsopoulos found that out with us: “Once we had our construction certificate through from council Chomp began our demolition and were finished within the 10 days they had promised.”

At a glance

  • Full project: typically 12 to 18 months end to end
  • Design and approval: roughly 4 to 8 months
  • Demolition and clearance: 5 to 15 working days
  • Asbestos phase: 1 to 3 days, and it runs before mechanical demolition
  • SafeWork NSW needs at least 5 calendar days’ written notice before licensed asbestos removal
  • Approval must exist before demolition begins
  • Service disconnections are the step owners most often get wrong

What is the full sequence?

Stage Typical duration Who runs it
Feasibility, survey and geotech 1 to 3 months Owner, architect
Design and documentation 2 to 4 months Architect, engineer
Approval, CDC or DA 2 to 4 months Certifier or council
Builder tender and appointment 1 to 3 months Owner
Service disconnections 2 to 6 weeks lead time Owner or builder
Asbestos testing and removal 1 to 3 days on site Licensed removalist
Demolition and site clearance 5 to 15 working days Demolition contractor
Excavation and site setout 1 to 3 weeks Excavation contractor
Construction 8 to 12 months Builder

The two long poles are approval and construction. Everything else is compressed, which is why delays in demolition hurt disproportionately: they land directly on the builder’s start date.

What happens in the demolition stage specifically?

  1. Approval confirmed and any conditions about tree protection or retention actioned
  2. Service disconnections completed and abolished
  3. Asbestos identification, then licensed removal if required, with SafeWork NSW notified at least five calendar days ahead
  4. Mechanical demolition, single storey typically 2 to 5 days
  5. Slab and footings removal if the new design does not reuse them
  6. Site clearance and levelling to the agreed level
  7. Handover to the builder or to the excavation phase

Step two catches more people than any other. A crew turning up to a site with live power cannot proceed, and that delay lands on your program, not theirs.

Why can’t demolition run ahead of approval?

Because the demolition is part of the approved development, not separate from it. Demolishing without consent exposes you to council enforcement action, and it can void insurance on the site. It also creates a problem at the other end: a certifier will not issue an occupation certificate for a building whose demolition was never approved.

Sequence it properly and the approval becomes the trigger that starts the clock, which is exactly what you want when a builder has given you a start date.

How should demolition slot into the builder’s program?

Backwards from the builder’s start, not forwards from today. Demolition, clearance and site setout all have to be complete before the builder’s first day, and excavation for the new build usually sits with the same contractor, so those phases should be quoted and programmed together rather than separately.

Our house demolition page covers the scope side, and our house demolition cost guide covers the budget side. If you are still choosing who does the work, our guide to what to check before appointing a demolition contractor is the starting point.

Frequently asked questions

Can I reuse the existing slab?

Sometimes, if it is sound and the new design suits it. More often it comes out, because the new footing design differs. Have it assessed rather than assumed.

Do I need to move out before demolition?

Yes. Services are disconnected and the structure comes down, so the property is vacant from the disconnection date. Plan the move before the notification period.

Who arranges the service disconnections?

Whoever is coordinating the project, usually you or your builder. We will tell you what has to be disconnected and when, but the applications sit with the asset owners.

Can demolition and excavation be one contract?

Often yes, and it is usually better. The two phases share plant, access arrangements and spoil removal, and separating them adds a handover and a remobilisation.

Planning a knock down rebuild? Contact us. We will walk the site, confirm the asbestos position and tell you exactly what the demolition stage involves before you commit to a builder’s start date. Chomp has worked on thousands of demolition and asbestos removal projects across Sydney.

Share this guide
Keep reading
All demolition guides
Free quote

Got a site that needs clearing, cutting or digging?

Tell us about the job and we will quote with asbestos, slab and disposal shown as separate lines.